SPRING CONSTRUCTION UPDATE 2019
Dear valued clients,
We are pleased to update you on the construction progress of Highline, Westmead
• A1, A2:
- Lift core and structure is now 100% complete
- External facade is now 60% complete
- Window installation is now 70% complete
- Internal fit-out is now 60% complete
• B1:
- Lift core and structure is now 100% complete
- External facade is now 40% complete
- Window installation is now 40% complete
- Internal fit-out is now 30% complete
• B2:
- Lift core and structure is now 100% complete
- External facade is now 65% complete
- Window installation is now 70% complete
- Internal fit-out is now 60% complete
Watch construction video here: